This process was repeated a further seven times. At the end of the day, the pipeline was stripped down and cleaned out. The following day the pump returned, the shut-off valves were removed, cleaned and coupled to the next batch of shutters and the pumping process re-commenced with the final nine shutters being filled. At the end of the second day, the pipeline was stripped down cleaned and stored back on the pump. The shut-off valves were stripped and cleaned the following day. After two days of work, all seventeen columns had been concreted from floor to ring beam above with no problem from concrete segregation or voiding.
-
Pump: M24
-
Customer: Mowlem Building
-
Site: Newcastle under Lyme
-
Concrete Supplier: Tarmac Topmix
-
Date: December 2004