With each pour coming in at around 180 cubic metres, the 140 cubic metre / hour pumps stroked slowly all day. In addition to pumping concrete to these two large tanks, Camfaud carried out a number of additional pours on site. Several bases were pumped for the steel process tanks that were erected on site and slabs poured for the site buildings and stores.
Throughout the contract, Camfaud worked closely with the main contractor, Galliford Try Meica JV, and the concrete supplier, Cemex, to ensure that the concrete mix used maintained its pumpability whilst meeting strict criteria in terms of strength and chemical resistance.
-
Pumps: M36 to M58
-
Customer: GTM (Galliford Try Meica)
-
Site: Kings Lynn Biosolids Treatment Centre
-
Concrete Supplier: Cemex
-
Date: October 2006 – May 2007